South Delhi-Noida line to be ready by year-end: DMRC

Hindustan Times | By
Apr 09, 2016 04:37 PM IST

Progress report says 3.9-kilometre Kalindi Kunj to Botanic Garden metro link is 67% complete, trials to begin on September 1

NOIDA: The Delhi Metro Rail Corporation (DMRC) in its progress report said the under-construction 3.9-km Kalindi Kunj-Botanic Garden Metro link is 67% ready and all set to be opened to public by December-end.

The DMRC submitted the report on Thursday saying work on Botanic Garden to Kalindi Kunj link is 67 per cent complete and trials will begin on September 1.(Burhaan Kinu/HT Photo)
The DMRC submitted the report on Thursday saying work on Botanic Garden to Kalindi Kunj link is 67 per cent complete and trials will begin on September 1.(Burhaan Kinu/HT Photo)

The DMRC submitted the report on Thursday after the Noida authority sought the same to know when the link between South Delhi and Noida will be operational, officials said.

HT launches Crick-it, a one stop destination to catch Cricket, anytime, anywhere. Explore now!

Also read: Delhi, UP should work together on high-speed Metro link

According to the progress report, the piling work on the track is 100% complete, 95% of pile caps are in place and 90% piers have already been installed along the corridor.

Once this Rs 845 crore corridor is ready, commuters will no longer have to go to Rajiv Chowk Metro station to take Line 2 (Huda City Centre to Jehangirpuri) as the corridor will form a ring route and connect Botanic Garden station with Hauz Khas station via Okhla Bird Sanctuary, Kalindi Kunj and Kalkaji stations.

According to Noida Authority officials, trials on the link, which will connect to DMRC’s magenta line, will begin from September 1, 2016.

“After conducting trials for four months, the Metro will be able to carry passengers,” said Pramod Kumar Aggarwal, additional chief executive officer of the Noida authority.

“We are satisfied with the progress of the work -- we are three months ahead of schedule. The first target for completion of the track was March 2017. As per the earlier schedule, the trials were supposed to start by December 2016,” Aggarwal said.

Also read: China-based agency will supply trains for Noida-G Noida metro

The civil work on the track will be completed by July 2016, officials said.

“The DMRC is carrying out electric work and laying of tracks. By April, laying of railway tracks on a 1.2 km stretch -- between Okhla Bird Sanctuary and Botanic Garden station -- will be completed. Currently, the DMRC is installing electric poles on this link,” said a Noida authority official.

Work on the track started in December 2014.Once this track is in place, Noida will have lines — the blue line and the magenta line. The progress report also said the 6.8-km City Centre to Sector 62 link is 15% ready.

SHARE THIS ARTICLE ON
Share this article
  • ABOUT THE AUTHOR
    author-default-90x90

    Vinod Rajput writes on environment, infrastructure, real estate and government policies in Noida and Greater Noida. He has reported on environment and infrastructure in Delhi, Gurgaon and Panchkula in the past.